Press Release Project Completion
Large Infrastructure Operational Program 2014-2020

Priority Axis 11 – Measures to improve energy efficiency and stimulate the use of renewable energy at the enterprise level
Thematic Objective – Supporting the transition to a low carbon economy in all sectors
Specific Objective 11.1 – Energy efficiency and use of energy from renewable sources for own consumption at the enterprise level.
“State aid measures for production from renewable energy sources”
31.12.2023
Press Release Project Implementation Completion "Renewable Energy Sources for KADRA TECH SRL"
KADRA TECH S.R.L., tax identification code 17696129, registered at the Trade Register under no. J12/2258/2005, located in Cluj-Napoca Municipality, Romania, Str. Tăietura Turcului no. 47, Cluj-Napoca Municipality, Strada TăieturaTurcului, No. 47, KADRA Building, Cluj County, postal code 400285, Romania, completed on
31.12.2023 the project titled “Renewable Energy Sources for KADRA TECH SRL“, SMIS code 160946, co-financed from the Cohesion Fund, through the Large Infrastructure Operational Program 2014-2020, implemented nationally by the Ministry of Investments and European Projects, through AM – POIM as the Managing Authority.
The total value of the project is 550,769.18 lei of which:
- 249,057.18 lei – Total eligible non-reimbursable value
- 211,698.60 lei – Eligible non-reimbursable value from CF
- 37,358.58 lei – Eligible non-reimbursable value from the national budget
- 203,774.06 lei – Co-financing
The general objective of the project:
The main objective of this investment plan is to increase energy efficiency, which will impact the reduction of GHG emissions, the development of clean energy sources at company level, achieving savings in annual primary energy consumption, and reducing the energy intensity of the company’s activity—contributing to the achievement of the European Union’s objectives for the 2021–2030 period, assumed nationally through the National Integrated Energy and Climate Plan 2021–2030 (PNIESC) regarding final energy consumption from renewable resources and increased energy efficiency. The project objectives are closely linked to the specific objective of the “Large Infrastructure Operational Program” (POIM 2014-2020), Priority Axis 11 – Measures to improve energy efficiency and stimulate the use of renewable energy at the enterprise level, investment priority 11.1 – Energy efficiency and use of energy from renewable sources for own consumption at enterprise level, namely ensuring energy efficiency and reducing consumption.
Expected results following project implementation:
- Photovoltaic system with an installed capacity of 70 kWp installed at the investment project implementation site, within the energy boundary targeted in the energy analysis.
- 81% of the annual electricity consumption for 2021 ensured from renewable energy sources based on the photovoltaic panel system installed during the project implementation period, within the energy boundary targeted in the energy analysis.
- Greenhouse gas emissions reduced by 81% compared to 2021, as a result of implementing the investment project, within the energy boundary targeted in the energy analysis.
Project implementation period:
2023-03-27 – 2023-12-31
Project co-financed from the Cohesion Fund, through
Large Infrastructure Operational Program 2014-2020